If you’re planning or already running a subdivision in Brisbane, Ipswich, Scenic Rim, Lockyer Valley or Somerset, Urban Utilities is making changes that will affect your water and sewer approvals.
Urban Utilities has released its Developer Customer Price List 2026-27, which takes effect on 1 November 2026. The way Information Requests work is also changing, the Developer Services Portal will be offline for a weekend, and the Christmas shutdown dates are out.
As an Urban Utilities endorsed consultant, Bravo Consult works with these processes every day. Here’s what the changes mean for your project and what to do before the deadlines.
Key dates at a glance
| Date | What happens |
|---|---|
| Fri 30 Oct 2026, 5:00pm | Portal goes offline. All applications still in Draft are deleted. |
| Mon 2 Nov 2026, 7:00am | Portal back online with the new fees and Information Request features |
| 1 Nov 2026 | New 2026-27 fees and charges take effect |
| Fri 20 Nov 2026 | Standard Water Approval or Works Request applications at Construction stage and site ready by this date will be completed before Christmas (weather permitting) |
| Thu 10 Dec 2026 | Last day to register a Planned Live Period in 2026 |
| Fri 18 Dec 2026 | Last day contractors can do live works in 2026 |
| Wed 23 Dec 2026, 4:30pm | Developer Services closes for Christmas |
| Mon 4 Jan 2027, 8:30am | Developer Services reopens |
| Tue 5 Jan 2027 | Third-party providers start works again (on or after this date) |
The new fees: more go down than up
Urban Utilities says that, before CPI is applied:
- 46% of fees will go down
- 29% will stay the same
- 25% will go up
The way fees are charged is also changing:
- Standard Connection applications will pay one fee per application.
- Non-standard Connection applications will pay one fee per network, for example drinking water and wastewater are each a separate network.
- Services Advice Notices (SANs) will be split into three levels: SAN Simple, SAN Preliminary and SAN Detailed.
Proforma invoices: if you pay a proforma invoice by its due date, the amount on it will be honoured. If it has expired, email DevelopmentEnquiries@urbanutilities.com.au for a new one. Fees after that are charged at the rate on the day the invoice is raised.
Fees that matter most for small subdivisions
These are some of the fees that come up most often on a typical small subdivision (prices marked * include GST):
| Service | 2026-27 fee |
|---|---|
| SAN Simple (pre-lodgement advice, up to 50 lots) | $1,381.60* |
| Standard Connection Assessment (per application) | $734.00 |
| Standard Connection Certification (per application) | $285.00 |
| Drinking water connection, same side of the road | $2,800.00 |
| Drinking water connection, up to the middle of the road | $4,987.00 |
| Drinking water connection, across the road | $6,547.00 |
| Sewer connection, connection point within the site | $2,745.00 |
| Sewer connection, works in the footpath/verge | $6,138.00 |
| Sewer works beyond 3m (per metre) | $117.00 |
| Non-standard Connection Assessment (per network) | $1,663.00 |
| Build Over Asset Referral | $754.00 |
These fees are separate from infrastructure charges, which are set under the Water Netserv Plan and can be a much larger part of your costs. Always check the full Developer Customer Price List 2026-27 for your project.
The Bravo view: the biggest difference in connection costs is often where the connection point is. Connecting on the same side of the road costs much less than connecting across it. Sorting this out early in the design is one of the easiest ways to keep servicing costs down.
Information Requests are changing
From 1 November 2026, Information Requests (IRs) in the Developer Services Portal will work differently:
- Better search and filtering. You can filter IRs by status, application type, application number, stage, address and due date.
- One extension per IR. An extension button appears five days before the due date. If approved, the extension runs for the same length as the original IR, starting from the original due date. Not every request will be approved.
- Confirm before you respond. You’ll have to confirm that every item in the IR has been answered before you can submit.
- Automatic reminders. You’ll get one reminder halfway through the response timeframe for every open IR.
- BOA/COA reminders. Reminders will be sent every 14 days for outstanding pre-construction items and every 90 days for post-construction items, until Urban Utilities accepts them.
The Bravo view: the new confirmation step means a partial response is now more likely to be noticed straight away. A complete, well-organised response the first time is the quickest way through. That’s where an experienced engineering consultant saves you weeks.
Notifications now go to every applicant
Previously, email notifications weren’t sent if an application had more than five applicants set to receive them. That’s now fixed: everyone with Notifications set to “Yes” will get emails, however many applicants there are.
Portal offline: lodge or save your drafts now
The Developer Services Portal will be offline from 5:00pm Friday 30 October until 7:00am Monday 2 November 2026.
Any application still in Draft at 5:00pm on 30 October will be deleted. If you have a draft in progress, lodge it before then or save your information somewhere else.
Planning works around Christmas
Developer Services closes at 4:30pm Wednesday 23 December 2026 and reopens at 8:30am Monday 4 January 2027.
If you want water connection works done before the break, your application needs to be at Construction stage and site ready by Friday 20 November 2026. Remember the 10 December cut-off for registering a Planned Live Period and the 18 December cut-off for live works.
Urban Utilities still runs 24/7 for faults and interruptions. Call 13 23 64 at any time, or log a fault online.
For Urban Utilities Developer Services, call 07 3432 2200 (8:30am to 4:30pm weekdays) or email DevelopmentEnquiries@urbanutilities.com.au.
Need help with your Urban Utilities approvals?
Bravo Consult is an Urban Utilities endorsed consultant specialising in small lot subdivisions across South East Queensland. We look after your water and sewer connection design, Information Request responses and Urban Utilities approvals, from concept through to plan sealing.
Book a free desktop site review and we’ll tell you what your subdivision will need before you lodge.
Source: Urban Utilities Developer Services Update (October 2026) and Developer Customer Price List 2026-27. Fees are as published by Urban Utilities and may change. Always check the latest price list before budgeting.